2015 Capital Project, completed in 2015
- $362,000 approximate site construction cost for site improvements at the high school.
- Reconstruction at front entrance and parking lot reconstruction.
2016 Capital Project, completed in 2016
- $2.7 million approximate site construction cost for site work at multiple school sites.
- Scope of services at the elementary school included: Asphalt patch at storm structure at the bus loop, regrout joints at granite curbs, replace asphalt walk, lawn repair.
- Scope of services at the middle school included: Repair service road and miscellaneous site improvements.
- Scope of services at the high school included: Synthetic turf replacement, athletic track repair including d-areas, asphalt, sidewalk, and curb replacement, baseball field improvements and softball field improvements.