creative • integrated • sustainable
Penn Yan Central School District
Penn Yan, NY

Penn Yan Central School District

2021 Capital Improvement Project
  • Site design at three schools.
  • Exterior stairs and drainage improvements.
  • New walkways and fencing, sidewalk replacement.
  • Pavement reconstruction at parking lots and bus loop, reconstruction of drop-off area.
  • Paved play area.
  • Site work related to site lighting.
  • Bleacher replacement with new concrete pad.
  • Site work associated with building additions.
  • Retaining wall replacement.
2017 Capital Improvement Project
  • Site work associated with a secured building entrance.
  • Parking lot and circulation improvements.
  • Replacement of synthetic turf field at Penn Yan Academy stadium.
  • Structural spray resurfacing of the athletic track and field events.
  • Installation of permanent lacrosse netting.
  • Fencing and gate replacement.
  • Site work associated with a new Transportation Center.

2012 Penn Yan Academy

  • Site work related to three building additions.
  • Scope of services included improvements to existing bus loop and front walkway, drop-off areas, sidewalks, installation of stairs, ramps, access road, parking lot, loading dock, and retaining wall, as well as development of a courtyard area.
  • Site preparation, grading, storm water management and drainage, circulation improvements, lawns and plantings.
  • Preparation of site sanitary plans and sanitary analysis.
  • Five new tennis courts, converting existing tennis courts into parking, and paving of the existing student parking lot.
  • Site plan preparation and site work associated with playscape replacement at the elementary school and installation of visitor bleachers at the athletic facility.
2004 Capital Improvement Project

Elementary/High School Additions

  • Responsible for evaluating numerous site configurations related to various additions to achieve the best solution for the school district.
  • Scope of site work included: a 400 meter all-weather track, multiple grass playfields, synthetic turf playing field, circulation and parking improvements.
  • Storm water management and realignment of a channelized stream.
  • Subsurface irrigation system for the synthetic turf surface.