• Renovation of the entire parking facilities including pavement replacement, circulation improvements, bus parking, new curbs and sidewalks.  Creation of a designated bus loading zone, safely separating bus, car and student conflicts.
  • Replaced deteriorated front entry steps at the original school building and incorporated an accessible ramp and ornamental handrails.
  • Drainage improvements implemented to meet current NYSDEC code compliance.

2018 Capital Improvement Project

  • New 6-lane track and field events, new multipurpose natural grass field within the track, new 200-seat bleachers.
  • Design of stadium entrance and pedestrian walkways.
  • Drainage improvements at athletic field including new underdrain system.
  • Parking expansion and site work related to new storage building.
  • Storm water management.