2015 Site Improvements (Capital Outlay Project)
- Septic system replacement and repair at Bolivar Road Elementary School.
- Pavement replacement at the high school which involved milling and re-topping 180,000 s.f. of asphalt.
2016 Site Improvements (Capital Outlay Project)
- Pavement replacement at the middle school which involved milling and re-topping 118,000 s.f. of asphalt.
2017 Site Improvements (Capital Outlay Project)
- Pavement replacement at Bridgeport Elementary which involves milling and re-topping 26,750 s.f. of asphalt.
- Reconstruction of paved play areas including running lanes, hopscotch, 4-square, and two half-court basketball areas.
2017 Capital Improvement Project
- Replacement of synthetic turf field and related athletic facility improvements.
- Front entrance restoration.