Portfolio » K-12 Education » Mohawk Central School District
Mohawk Central School District
| Approximate Site Cost: $3.7 Million total | Completed: Multi-Phase Project |
Phase 1, completed in 2009
- $3.4 million approximate site construction cost for site work at the elementary and Jr./Sr. High School.
- Scope of services at Fisher Elementary School included a new bus loop with access drive, new playground, installation of a 12+ foot modular retaining wall, ADA walkways and granite curbing, and circulation improvements at the main parking lot.
- Athletic field improvements at Fisher Elementary School include a sodded overlapping multi-purpose softball field, 1,000 seat bleachers, press box and additional parking.
- Site work at the Jr./Sr. High School included reconstruction of a 9+ foot modular retaining wall, drainage improvements to an existing athletic field, and parking lot drainage improvements.
Phase 2, construction began Summer 2011
- $246,000 approximate construction cost for additional work at Fisher Elementary.
- Scope of services include pool demolition and infill, and drainage improvements at the entrance drive.